Time to complete is opened by selecting Data on the very top menu bar or by opening Tasks on the main menu bar and right clicking a Task and selecting Time to Complete. The following form opens with a list of Tasks. Search and filter opens are available to narrow down to the specific Task:

...

Above the we have 0.39 actual hours logged as labor and the inherited Task budget of 1.34 hours leaving a remainder or 0.95 hours (time to Complete).

We may decide that we need to increase the Tasks budget without affecting the original budget and insert an additional 2 hours, now the task budget (Inherited budget of 1.34 + 2 hours Task budget increase) has increased to 3.34, leaving a Time to complete the Task of 2.95 hours ( 3.34 - Actual labor(0.39) ) :

...

Remember to save these changes before exiting this form.

...