Open the Project form > Contract tab.

Contract values are added and managed in the upper section.

All values start at $0 by default.

Enter the contract value in the “Contract : Original” box

Other values shown are calculated from the Schedule of Values (SOV) and Change Orders, and cannot be edited directly.

Contract tab contains four sub-tabs. Right-click in the fields to add items and edit properties.

...